Federal law · Public Law 119-90 · Hydropower licenses · Section 1
Extra time may be granted to start certain hydropower construction
When it was enacted
Before
The Federal Power Act generally allowed the Federal Energy Regulatory Commission to extend the time to start construction of a licensed project for up to 8 years.
After
For qualifying hydropower projects licensed before March 13, 2020, the Commission may grant up to 6 additional years, in as many as three consecutive 2-year periods, when the licensee requests it and shows good cause.
Enacted sourceIn plain English
Some older hydropower projects can get up to six more years to begin construction if the regulator approves the request.
Timing and applicability
The law was enacted May 11, 2026. Its special extension authority applies only to the covered projects it defines.
Interpretations & later changes
Later-law and court review may be incomplete. Absence of an entry does not establish that the original provision remains in force.
No separately reviewed later development is published here yet.