Project-sponsor fees for environmental reviews

When it was enacted

Before

The National Environmental Policy Act did not contain this section 112 process for a project sponsor to pay an opt-in fee for an environmental assessment or environmental impact statement.

Earlier official source

After

The law adds NEPA section 112. A project sponsor may submit project information to the Council on Environmental Quality and, after notice, pay a fee equal to 125 percent of the anticipated preparation or supervision costs. A paid environmental assessment must be completed within 180 days after payment, and a paid environmental impact statement within one year after the notice of intent.

Enacted source

In plain English

A project sponsor can now choose to pay for an environmental review. The law sets the fee at 125 percent of estimated costs and sets timelines for completing the review.

Timing and applicability

The enacted section has no separate delayed effective date.

Interpretations & later changes

Later-law and court review may be incomplete. Absence of an entry does not establish that the original provision remains in force.

No separately reviewed later development is published here yet.