← D.C. Law 25-274 · All reviewed explanations
D.C. Law 25-274 · DC District of Columbia · Section 2
Which underground utility jobs and employers are covered
When it was enacted
Enacted 2025-01-09 · Effective 2025-03-07 · Permanent law.
Official record datesWhat this builds on
This standalone act creates a wage framework and supplies its own coverage definitions; this section does not repeal other wage protections.
What this creates
A covered employer is a gas- or electric-utility contractor on an underground-work contract over $250,000. Covered work requires the specified excavation permits and includes necessary construction tasks and traffic control. The act uses existing statutory definitions of gas and electric companies.
Enacted sourceIn plain English
The wage rules target qualifying underground utility contracts, not every job done for a utility. Traffic-control work needed to complete the covered project is included. The contract must exceed $250,000.
Timing and applicability
The Law Library lists March 7, 2025 as the effective date. Sections 7 and 8 separately address the 180-day delay and inclusion of the fiscal effect in an approved budget. The actual funding-trigger date has not been verified here; March 7 alone does not establish when a worker became entitled to payment.
Explanation reviewed 2026-10-22.
Read the official section text
2 Definitions. (a) For the purposes of this act , the term: (1) "Covered employer" means a contractor of a gas company or an electric company contracted to perform underground utility work in a contract amount over $250,000. (2) "Davis-Bacon Act" means An Act Relating to the rate of wages for laborers and mechanics employed on public buildings of the United States and the District of Columbia by contractors and subcontractors, and for other purposes, approved March 3, 1931 (46 Stat. 1494; 40 U.S.C. 3141 et seq ). (3) "Electric company" shall have the same meaning as in section 8 of An Act Making appropriations to provide for the expenses of the government of the District of Columbia for the fiscal year ending June thirtieth, nineteen hundred and fourteen, and for other purposes, approved March 4, 1913 (37 Stat. 976; D.C. Official Code § 34-207) ("Act"). (4) "Gas company" shall have the same meaning as in section 8 of the Act (D.C. Official Code § 34-209) . (5) "Prevailing wage" means the wage paid to specified categories of workers, as described in section 3 , doing underground utility work. (6) "Underground utility work" means work pursuant to a contract awarded to a covered employer by a gas company or an electric company in an amount over $250,000 for which a permit is required under section 6 of the Underground Facilities Protection Act of 1980, effective March 4, 1981 (D.C. Law 3-127; D.C. Official Code § 34-2705) ("Underground Facilities Protection Act") or D.C. Official Code § 47-2718 to excavate a street or other public space for the purpose of installing, maintaining, replacing, demolishing, as defined in section 2(1) of the Underground Facilities Protection Act (D.C. Official Code § 34-2701(1)) , or removing a utility line or underground facility. The term includes traffic control and all other construction tasks necessary to perform and complete the underground utility work.Pinned official bulk source
Interpretations & later changes
Later-law and court review may be incomplete. Absence of an entry does not establish that the original provision remains in force.
No separately reviewed later development is published here yet.